May 2, 2018 5:40PM BST
Scheduled - Background Summary

Node4 are committed to delivering the best possible network service and uptime.
We continually invest in our infrastructure to meet customer requirements and capacity demands.
During the next two months engineers will be installing new core routers in to our data centres.
These core routers will support MPLS and Internet Transit services.

This work is not expected to have any impact on connectivity and cloud services however there will be increased risk during the maintenance.
The core network uses a resilient design, some of this resilience will be temporarily reduced during the maintenance window.
Engineers will also be costing out links and enabling new routing peers which has the potential to cause transient network connectivity while routing convergence occurs.

DC-4 Part 1 - 00:00-05:00 BST Wednesday 16th
DC-4 Part 2 - 00:00-05:00 BST Thursday 17th

Preparation work will commence at 00:00 with changes commencing at 01:00

We encourage all our customers to please check our network status page http://www.n4status.com during the maintenance updates and tracking.

Our network operations engineers will closely monitor the work and will do everything possible to minimize any inconvenience to you. If you have any problems with your connection after this time, or if you have any questions regarding the maintenance at any point, please contact Node4 Technical Support

Regards
Node4 Technical Support


May 16, 2018 12:37AM BST
Active - Maintenance will commence at 01:00 as scheduled. Further updates to follow.

May 16, 2018 2:31AM BST
Active - Maintenance is continuing as planned. Further updates to follow.

May 16, 2018 3:08AM BST
Completed - Maintenance has been completed successfully without any service impact. This maintenance window is now closed.